IOHA Report to ILO on an International OHSMS - Appendix C/21
[Title page] [Table of Contents] Chapters: I II III Appendices: A B C D E F G |
Analysis Summary
|
A. Review Issues and Questions
|
1. |
Publication date. |
1992. |
|
2. |
Status: final, draft, other. |
Final. |
|
3. |
Pending revisions. |
No. |
|
4. |
Publishing Organization type. |
Industry association. |
|
5. |
Type of OHSMS. |
Voluntary code of practice. |
|
6. |
Is it used by regulatory agencies to achieve agency mandate? |
No. |
|
7. |
Is it meant to be an auditable standard? |
Yes. |
|
8. |
Is it used as an auditable standard? |
Yes. |
|
9. |
Is it a management system? |
Yes. |
|
10. |
Are there technical appendices? |
No. However, there are other Responsible Care codes of practice that support this code. |
|
11. |
Is there a companion audit guidance document? |
Yes. |
|
12. |
Are there stated limitations of use? |
No. |
B. Review Comments
This Code of Practice has been developed by the Chemical Manufactures’ Association. Its purpose is stated as:
The goal of the Employee Health sand Safety Code of Management Practices is to protect and promote the health and safety of people working or visiting member company work sites.
To achieve this goal, the Code provides Management Practices designed to continuously improve work site health and safety. These practices provide a multidisciplinary means to identify and assess hazards, prevent unsafe acts and conditions, maintain and improve employee health, and foster communication on health and safety issues.
Implementation of the Employee Health and Safety Code, together with other Codes of Management Practices, can enable member companies to operate in a manner that further protects and promotes the health and safety of employees, contractors, and the public, and protects the environment.
This is a short Code of Practice. Three pages.
It is comprehensive and uses "shall" statements.
Missing system variables include:
- regulatory, compliance and OHSMS conformance
- goals and objectives
- hazardous agent management
- integration.
Continual improvement is stated in the preamble, but not in the Management Practices category.
Self-inspections not explicitly mentioned.
C. Outline
• Program Management
• Identification and Evaluation
• Prevention and Control
• Communication and Training
D. Analysis Checklist
|
|
Management System Variable |
|
Notes |
|
1.0 |
Management Commitment and Resources |
x |
|
|
1.1 |
Reg. Compliance and OHSMS Conformance |
|
|
|
1.2 |
Accountability, Responsibility, and Authority |
x |
|
|
2.0 |
Employee Participation |
x |
|
|
3.0 |
Occupational Health & Safety Policy |
x |
|
|
4.0 |
Goals and Objectives |
|
|
|
5.0 |
Performance Measures |
|
|
|
6.0 |
System Planning and Development |
x |
To be performed on-going. |
|
6.1 |
Baseline Eval. and Hazard/Risk Assessment |
x |
|
|
7.0 |
OHSMS Manual and Procedures |
x |
|
|
8.0 |
Training System |
x |
|
|
8.1 |
Technical Expertise and Personnel Qualifications |
x |
|
|
9.0 |
Hazard Control System |
x |
|
|
9.1 |
Process Design |
x |
|
|
9.2 |
Emergency Response |
x |
|
|
9.3 |
Hazardous Agent Management |
|
|
|
10.0 |
Preventive and Corrective Action |
x |
|
|
11.0 |
Procurement and Contractor Selection |
x |
|
|
12.0 |
Communication System |
x |
|
|
12.1 |
Document and Record Management System |
x |
|
|
13.0 |
Evaluation System |
x |
Can be inferred. |
|
13.1 |
Auditing and Self-Inspection |
x |
|
|
13.2 |
Incident Investigation and Root Cause Analysis |
x |
|
|
13.3 |
Medical Program and Surveillance |
x |
|
|
14.0 |
Continual Improvement |
x |
Not explicit. |
|
15.0 |
Integration |
|
|
|
16.0 |
Management Review |
x |
|
|